During integration week, there have been daily meetings everyday at 10 AM UK time. We would gather together and the PL and DPL would give tasks to be completed. This week was a clean up of the code, and we conducted a lot of testing together in groups. Where if one task was finished, we would be allocated a new task.
Coding time: 2-3 Hours
Meetings: 4 Hours
JUnit Testing: 3-4 Hours
Total Time: 10-12